Recommendation |
Time Frame |
| 25 |
Paint any boxes that cannot be buried the same color as streetlight poles |
6-18 months |
| 26 |
Require vegetation over any underground utilities |
1-5 years |
| 27 |
Place cellular antennas away from scenic corridors |
1-3 years |
| 28 |
Re-nogotiate franchise agreements to recognize scenic corridor criteria |
2-12 years |
| 29 |
Change cross-section to show unpaved paths; ban concrete sidewalks |
6-24 months |
| 30 |
Locate and buffer trails away from pavement |
6-18 months |
| 31 |
Use of alternative layouts may place paths in ROW and setbacks |
See. #30 |
| 32 |
Use serpentine or curving designs along contours for paths |
1-5 years |
| 33 |
Consider public installation of continuous paths/trails along scenic
corridors |
2-5 years |
| 34 |
Use desert tones and materials for headwalls and other drainage
improvements |
1-4 years |
| 35 |
Keep wet crossings whereever possible |
1-2 years |
| 36 |
Provide bridges/culverts and design with vertical undulations |
See #35 |
| 37 |
Where bridges/culverts are required, use if possible, as trail a crossing |
6-24 months |
| 38 |
Preserve the existing drainage pattern (per ESLO) |
1-4 years |
| 39 |
100' minimum scenic corridor setback/easement |
1-10 years |
| 40 |
Where it is not feasible to achieve through development review process,
city purchases corridor |
See #39 |
| 41 |
No master planned entry monuments or signs within the corridor |
See #17 |
| 42 |
Paths or trails in the setbacks should blend with desert setting |
See #30 |
| 43 |
Natural washes are acceptable in corridor, but other drainage features are
not |
See #38 |
| 44 |
No walls should be permitted in setback |
6-18 months |
| 45 |
Street signs, lights, sign, monuments, gates, gate houses not allowed in
corridor |
See # 16, #18, #19, #24 |
| 46 |
Minimize the number of street and driveway crossings |
See #7 |
| 47 |
Preserve existing vegetation and maintain natural density |
See #11, #12, #14 |
| 48 |
Develop maintenance guide defining what is appropriate within corridors |
See #13 |
| 49 |
Revegetation may add plants to the corridor |
See #15 |